Pavement Works:-Gerard Street

The next phase of the town centre improvement scheme is outlined below.

The proposed pavement improvements are to be carried out to the front of numbers 25-41 Gerard Street. Following consultation the residents in this area will be notified that the work are programmed to begin on Monday 7th July.

However, the start date depends on Wigan council's contractor not having been delayed by poor weather elsewhere.

The contractors will begin by replacing the kerbs and rebuilding the pavement with block paving similar to that used on the footway along the opposite side of Gerard Street.

If you have any questions about the works, residents can contact Steve Hughes Area Engineer (Highway Maintenance)on 404364.